Relocation of 600 tonne woolpress from Wellington to Fairlie Woolscour's Timaru plant; Refit of 500 tonne Woolpress

Fairlie Woolscour

Location    Washdyke, Timaru
Project:      Relocate Woolpress; Refit Woolpress

 

Project 1: The upgrade of a 500 tonne woolpress to improve plant reliability and the ability to provide local technical support for a specialised piece of plant 

The upgrade of this machine was no small task due to the fine operating tolerance of the machine and the sheer capabilities of the hydraulic plant. The tolerance of the valve timing sequence on this machine was within milliseconds to achieve correct operation. The batch weigh system was incorporated into the automation process and was very critical to achieve maximum container weights. 

"The project's success was due to a determination to deliver a functional and reliable machine." 

Trevor Cook, Plant Manager, Fairlie Woolscour Ltd.


Project 2: Relocation of the 600 tonne Autefa woolpress from Seaview in Wellington to Fairlie Woolscour's Timaru plant. 

"The ICSC installation team delivered a successful and cost effective project once again. Everything went very smoothly and the machines are working fine. We are more than happy" 

Trevor Cook, Plant Manager, Fairlie Woolscour Ltd.

<h2>Let's work together</h2>

Let's work together

Specialists in industrial electrical & automation systems.

A growing company with a strong commitment to customer service and technical excellence.

Let's work together

52 Bank Street, Timaru, 7910,
New Zealand

sales@icsc.co.nz