Location Ashburton
Project Installation of a 10MW coal fired boiler
Project: Electrical and instrumentation installation, commissioning and as-built documentation of a 10MW coal-fired boiler for the Ashburton plant expansion.

This project involved providing Easteel with the site installation team for a 10MW unattended coal-fired boiler. This included interfacing the new boiler system into the current ash and coal handling equipment on site.

"The successful completion of this project can be put down to the dedication of the ICSC installation team delivering 100% for the client to meet a very tight deadline"

Brendan Stevenson, Service Manager, Easteel Industries Ltd.